Midtown Tampa Development

Previous
Next

Midtown Tampa Development – Tampa, FL

MidTown Tampa is a new 1.8 million-SF hotel-retail-office-housing development located in the WestShore District. Once complete, the complex will include approximately 240,000-SF of retail and entertainment space; 186,000-SF of Class A office space; 400 condos and/or apartments and a 225-room boutique hotel. Currently, Barr & Barr’s scope of work includes: All underground site utilities and building pads, final landscaping and hardscaping for the entire 22-acre site. Offsite work includes: Additional roadway signalization and turn lanes, repaving and milling asphalt, striping, all work in public roadways – $10 million. West Office Tower: Core & Shell construction of 186,000-SF, eight-stories and $32 million. Includes pedestrian bridge connecting to parking deck, plus first floor retail space (REI, sundries store, etc.) and lobby. Building H – Three-story retail and office space, 74,000-SF and $9.5 million. Megadeck Parking Garage: Stand-alone deck, six-stories and 350,000-SF including 1,100 spaces, $17.5 million. Whole Foods Grocery Shell & five-story parking garage: Whole Foods store is 55,000-SF, Parking garage which will be built above the grocery space is five-stories, approximately 300,000-SF and 750-spaces. Management of entire 22-acre site throughout the multi-year life of the project including all facilities such as office, retail, hotel, and multi-family.

FACTS

Size: 186,000 SF (Office Building)
Schedule:Multiple durations: West Office Tower – 19 Months Whole Foods & Parking Garage – 14 Months Megadeck Parking Garage – 12 Months
Contract Type:Construction Manager-at-Risk
Owner: Bromley Companies
Architect:Multiple: TVS Design (Office Building), WDG Architects (Whole Foods) and Finfrock (Megadeck Parking Garage)

Midtown Tampa Development

TAKE THE NEXT STEP